Czech plant targets March 2028 start-up, while Greek, Swedish projects move towards equipment orders
Dillingen, Germany – Pyrum Innovations is progressing several European end-of-life tire (ELT) pyrolysis projects, with construction under way in the Czech Republic and new funding developments supporting proposed facilities in Greece and Sweden.
In a 5 Nov investor podcast, CEO Pascal Klein said the company had completed the sale of its first tire recycling plant to the reTIRE project in Sokolov, Czech Republic.
"The plant purchase agreement has been signed, down payment has been made," Klein confirmed.
Construction is progressing, with foundations under way, buildings ordered and long-lead equipment being procured.
The project has also secured bank financing covering "almost 70%" of the investment.
Pyrum is targeting March 2028 for the start of operations at the Sokolov facility.
Klein said the company was also working to finalise a revised dosing system for its recovered carbon black (rCB) milling and pelletising equipment, which will be incorporated into future plants.
The equipment must be selected in time for ordering for the Czech project by the end of March 2027, according to the CEO.
The system is intended to enable future Pyrum plants to process different rCB grades, including the new "new standard" material developed with Continental.
Greek plant negotiations
Meanwhile, Pyrum has completed the redesign of its proposed tire recycling plant in Greece, following the award of a €29.4 million grant.
Klein explained that the grant required the originally planned three-reactor facility to double in size to six reactors.
"That grant has changed the design of the plant," he said.
The larger project would generate significantly higher equipment sales for Pyrum and become, according to Klein, the "biggest tire recycling unit in whole Greece."
However, the expansion required extensive redesign work during the first three quarters of 2026.
"But that is done now," Klein confirmed.
Pyrum submitted its final binding offer by the end of August and is now negotiating the contract with its Greek customer.
The CEO said discussions were focused on costs, equipment specifications and potential savings.
The project is expected to reach the ordering stage before the end of 2026 to comply with the grant conditions.
"According to the grant contract, they need to order it before the end of the year," Klein said.
Pyrum, therefore, said it remained confident that it could complete a second plant sale before year-end.
"We are very confident that maybe this year we are not just selling one plant, but two," he said.
Swedish project revived
In Sweden, Pyrum's proposed tire recycling project with GreenTech has returned to the company's priority list following the award of a €24 million grant.
Klein said progress had previously been slow because the project's financing remained uncertain.
"Sweden is a project that was more in the background in the last months because the financing there was not very clear," he explained.
However, GreenTech informed Pyrum several weeks earlier that it had secured the funding.
"Suddenly the project comes into the first rang now," Klein said.
"It becomes one of our primary projects because suddenly, things move there very quickly because the financing is there."
Pyrum now hopes to announce the start of the Swedish project and the sale of the associated plant in the coming weeks or months.
"Hopefully we can soon announce that the project has actually started, and the plant has been sold," Klein added.